New BG Railway Line from Harmuti to Itanagar (33 Km).
Railway Project
Date of Commencement : Feb’1997
Schedule date of completion : Harmuti-Naharlagun : March’2012(T)
Brief description of project : New BG Railway Line Project is taking off from Harmuti
station of Rangiya – Murkongselek section under going Gauge Conversion from MG to BG and connecting capital of Arunachal Pradesh i.e. Itanagar. The Project was sanctioned during year 1996-97. Part Detailed estimate from Harmuti to Naharlagun was sanctioned by Rly. Board on 31.01.2008 at a cost of Rs.160.48 Crs. Detailed estimate for balance section i.e. Naharlagun to Itanagar at a cost of Rs.371.33 Crs. has been sent to Railway Board on 7.7.2009 for sanction.