Saturday, February 26, 2011

Railway Project Kumarghat – Agartala New Line (109 Km)


Railway Project

Kumarghat – Agartala New Line (109 Km)

1.0  Month of Review   : November,2010  

2.0  Salient Feature    : 

2.1  Name of the project   : Kumarghat – Agartala New Line (109 Km) 
             
2.2  Implementing Agency   : N. F. Railway, Construction Organisation. 

2.3  Length of the Railway line  : 110 Km 

2.4  Estimated Cost    : Rs.984.97 Crs. 

2.5  Date of Commencement   : July’1996 

2.6  Schedule date of completion  : March – 2014 (T)

2.7  Brief description of project : To connect  state capital of Tripura with rail network and to develop backward region of  remote state of Tripura in Northeast. Project  completed and MG services commissioned w.e.f.  05.10.2008.  